Notes from Rosi:
Shifts will start Feb 18 in order to give the TPC group the float necessary to be ready for the field-on no beam data from ~March 26
Local (including SBU) folks will be encouraged to take these, the start date may change
TPC Prerequistes:
Driver 2 and rev E boards to arrive by Jan 6 - stuff, install, test by end of Jan
Switch from MUX to NIM-MUX --> Need modules from HEAP, maybe get some from SBU, checking on all the hardware (i.e fan outs) is important
Week of Jan 6 for cosmics (no Isobutane) to test Caen, need to see signal in each module
New Firmware will require a lot of effort (will be given priority over other TPC tasks)
Testing the entire system with the driver 2, rev E, NIM-MUX, digitizers and the trigger will also take some time --> Use the test time in February prior to gas, but may/will go into the gas time
FEE repairs will also need to be scheduled during this time